| Water and Sanitation Programme |
|
|
|
|
Project - 3 year- ACP-EU Watsan in Mt Darwin District, Mashonaland Central Province Funding - ACP-EU (British and Finish Red Cross)
Activities/Targeted- Drilling of bores 70 • Rehabilitation of water points 110 • Construction of latrines 1200 • Training of builders 220 • Community based management (CBM) training 70 committees • Sand water abstraction 10 • Hygiene promoters training 220 • Pump minders training 400 • Hygiene promotion into the community target 100 000 people
Achievements
• Drilling of bores 70 • Rehabilitation of water points 150 • Construction of latrines 1135 • Training of builders 220 • Community based management (CBM) training 207committees • Sand water abstraction 7 • Hygiene promoters training 254 • Pump minders training 60 111 576 people received hygiene education through PHAST methodology
Comments The project was extended for 4 more months. It will be ending on 31 February 2009
Sand abstraction is a new technology which draws water from the river bed. The technology is ideal for livelihood gardens More water points need rehabilitation. 50 more water points are going to be rehabilitated during the extension period since the budget line has not been exhausted. If money remains by end of project, back spares will be purchased for the local council to operate a spares bank We decided to reduce on the number of pump minders to be trained. It was learnt that newly trained pump minder without experience were dropping pipes during pump repair
Project - 6 Months - Appeal Food Security and Livelihood (WatSan) in Beitbridge - Matabeleland South, Dete – Matabeleland North and Chivi – Masvingo.
Funding – IFRCS Activities/Targeted- • Rehabilitation/repair of 200 water points • Fitting and construction of 100 animal water drinking troughs • ToT training of 16 volunteers and 4 provincial field officers on PHAST • Community based management refresher training of 200 committees Cascading of hygiene promotion to safe water beneficiary communities totaling 20 000
Achievements • 200 water points Rehabilitated/repaired • 100 animal water drinking troughs Fitting • 16 volunteers and 4 provincial field officers trained as ToTs on PHAST • 200 CBM teams refreshed 20 000 safe water beneficiaries receive hygiene promotion training
Comments All activities were carried out by end of September 2009 Same of the rehabilitated water points need apron and waste water run away channel repair ( provinces did not consider requesting cement for the construction of apron and waste water run away channel) this was due to lack of knowledge among the field officers. There is need to train field officers on WatSan issues It has been learnt that there are materials left over at the IFRC ware house. If a budget can be made available these materials can be used for perfection of the rehabilitated water points.
Project - 6 Months - ECHO Mwenezi Food Security (WatSan) Funding - ECHO
Activities/Targeted- • Construction of elephant pumps 20 Construction of 20 animal water drinking troughs
Position • 20 elephant pumps constructed 20 animal drinking troughs constructed
Comments Project completed
Project - Danida Food Security and Livelihood Watsan in Mat. South (Beitbridge), Mat North (Nkayi), Masvingo (Mwenezi) Funding - Danish Red Cross
Activities/Targeted- • To repair/rehabilitate 135 water points • To construct 135 animal drinking troughs • To carry out CBM refresher training for 135 water point committees Construction of sand water abstraction pumps and gardens 30
Position
• Implementation work plans, budgets and cash requests were made at provincial leve • Spares assessments are under way
Procurement is in progress
Comments The project is running up to June 2010 as for Masvingo and Mat. North. Mat south will run up to December 2009
Project - Chitungwiza water works rehabilitation and software Funding - French Red Cross
Activities/Targeted- • Repair of Prince Edward water works Hygiene promotion in Chitungwiza’s unit D and NFI distribution
Position
People reached by hygiene education Male adults - 5 396 Female adults - 6 089 Male child - 4 851 Female child - 4 961 Total - 21297
Distribution of non food Items NFIs buckets,IEC,soap, water makers, aqua tablets The repair of the water works was done through French Red Cross Engineer
Comments The project is now complete. This was Medium team watsan intervention after the cholera outbreak Detailed report on work done at the water works still to come from the French Red Cross Engineer
Project - Kadoma and Chegutu water works rehabilitation and Software
Funding - French Red Cross
Activities/Targeted- • To carry out water works rehabilitation at Kadoma and Chegutu To carry out hygiene promotion in Chegutu and Kadoma
Position Proposal ( logical frame work, budget and implementation plan) prepared awaits ECHO and UNICF approval ( Funders of French RC) Comments The project will be implemented in the same way as the Chitungwiza above Hardware FRC soft ware ZRCS
Proposed Project - Germany Proposal
Funding - German Red Cross Proposal
Activities/Targeted- Rehabilitation and trainings Position Concept submitted to German Red Cross for possible funding to the tune of 800 000Euro ear marked Comments Pending
Proposed Project - ACP-EU Proposal Funding - German/ACP-EU Proposal Activities/Targeted- As per Mt Darwin ACP-EU Watsan project
Position Log frame submitted as per request Comments
Pending - Target areas: Mbire and Mberengwa |